City of Houma, energy and gas end of day report, Monday, Sept. 6

Entergy/Terrebonne end of day report, Monday Sept. 6
September 6, 2021
Retail stores, restaurants, gas stations: See what’s open in the Houma area today
September 6, 2021
Entergy/Terrebonne end of day report, Monday Sept. 6
September 6, 2021
Retail stores, restaurants, gas stations: See what’s open in the Houma area today
September 6, 2021

CITY OF HOUMA ELECTRIC AND GAS:  9/6 End of the day update.

 

Damage assessments have reported a total of 194 broken poles, 494 leaning/down poles, 474 locations of down/broken primary and secondary wires, 107 damaged transformers, 322 damaged crossarms, 890 damaged insulators and 105 damaged streetlights.


 

As of 09/06/2021 (226) of the accessed poles have been repaired or replaced and are back in working condition pending Entergy’s transmission completion on Wednesday 9/8/21.

 

115 KV Transmission ‐100 % complete with damage assessment.

‐ 3 broken poles


‐ 2 leaning/down poles

‐ 6 different locations of down/broken primary and secondary wires

‐ 19 insulators damaged


‐ 4 damaged crossarms

‐ 3 damaged transformers

(Repaired 11 substations. 2.5 miles of 115KV and 22 Miles of 34.5KV )


 

Cummins 3 feeder – 10% complete with damage assessment.

‐ 4 broken poles

‐ 2 leaning/down poles


‐ 4 different locations of broken primary wires

‐ 7 damaged insulators

‐ 4 damaged crossarms


 

Dumas 1 feeder ‐100% complete with damage assessment.

‐ 6 broken poles

‐ 19 leaning/down poles


‐ 27 different locations of down/broken primary and secondary wires.

‐ 7 damaged crossarms

‐ 2 damaged transformers


‐ 21 damaged insulators

 

Dumas 2 feeder – 100 % complete with damage assessment.

‐ 3 leaning/down poles


‐ 1 broken secondary wire

 

Loop 1 – 100% complete with damage assessment

‐ 1 broken pole


‐ 6 leaning/ down poles.

‐ 3 different locations of down/broken primary wire.

‐ 6 damages crossarms


 

Loop 3 – 100% complete with damage assessment

‐ 24 broken poles

‐ 36 leaning/down poles


‐ 79 different locations of down/broken primary and secondary wire

‐ 23 damaged cross arms

‐ 9 damaged transformers


‐ 4 damaged streetlights

‐ 35 damaged insulators

 

McKinley 1 feeder – 100% complete with damage assessment


‐ 3 broken poles

‐ 12 leaning/down poles

‐ 27 different locations of down/broken primary and secondary


‐ 20 damaged insulators

‐ 8 damaged crossarms

‐ 3 damaged transformers


‐ 3 damaged streetlights

 

McKinley 2 feeder – 100% complete with damage assessment

‐ 4 leaning/down poles


‐ 3 different locations of down/broken primary and secondary wire

‐ 1 damaged transformer

 

McKinley 3 feeder – 100% complete with damage assessment


‐ 2 broken poles

‐ 1 leaning/down poles

‐ 13 different locations of down/broken primary and secondary wire


‐ 4 damaged insulators

‐ 1 damaged crossarm

‐ 1 damaged streetlight


 

Norman Sub – 100% complete with damage assessment

‐ 50 broken poles

‐ 76 leaning/down poles


‐ 202 different locations of down/broken primary and secondary wire

‐ 552 damaged insulators

‐ 157 damaged crossarms


‐ 29 damaged transformers

‐ 7 damaged streetlights

 

Plant Road 1 feeder – 100% complete with damage assessment


‐ 2 broken poles

‐ 1 leaning/down poles

‐ 16 different locations of down/broken primary and secondary wire


‐ 16 damaged insulators

‐ 2 damaged crossarms

‐ 3 damaged transformers


‐ 7 damaged streetlights

 

Sherwood 1 feeder – 50% complete with damage assessment. Will be 100% complete by end of day 09/06/2021

‐ 3 broken poles


‐ 11 different locations of down/broken primary and secondary wire

‐ 7 damaged insulators

‐ 4 damaged crossarms


‐ 1 damaged transformer

‐ 3 damaged streetlights

 

Sherwood 2 feeder – 100% complete with damage assessment


‐ 12 broken poles

‐ 11 leaning/down poles

‐ 38 different locations of down/broken primary and secondary wire


‐ 36 damaged insulators

‐ 11 damaged crossarms

‐ 7 damaged transformers


‐ 4 damaged streetlights

 

Six Street feeders 1&2 – 100% complete with damage assessment.

‐ 19 broken poles


‐ 73 leaning/down poles

‐ 64 different locations of down/broken primary and secondary wire

‐ 38 damaged insulators


‐ 22 damaged crossarms

‐ 14 damaged transformers

‐ 4 damaged streetlights


 

Southdown 1 feeder – 99% complete with damage assessment. Will be 100% complete by end of day 09/06/2021.

‐ 5 broken poles

‐ 24 leaning/down poles


‐ 24 different locations of down/broken primary and secondary wire

‐ 4 damaged insulators

‐ 3 damaged crossarms


‐ 3 damaged transformers

‐ 3 damaged streetlights

 

Southdown 2 feeder – 100% complete with damage assessment


‐ 5 broken poles

‐ 30 leaning/down poles

‐ 15 different locations of down/broken primary and secondary wire


‐ 24 damaged insulators

‐ 9 damaged transformers

‐ 10 damaged crossarms


 

Southdown 3 feeder – 100% complete with damage assessment

‐ 14 broken poles

‐ 81 leaning/down poles


‐ 125 different locations of down/broken primary and secondary wire

‐ 20 damaged insulators

‐ 17 damaged crossarms


‐ 8 damaged transformers

‐ 7 damaged streetlights

 

Southdown 4 feeder – 100% complete with damage assessment


‐ 7 broken poles

‐ 8 leaning/down poles

‐ 25 different locations of down/broken primary and secondary wire


‐ 7 damaged insulators

‐ 5 damaged crossarms

‐ 2 damaged transformers


‐ 3 damaged streetlights

 

Plant Road 2 feeder – 15% complete with damage assessment. Will be 100% complete by end of day 09/06/2021

‐ 3 leaning/down poles


‐ 6 different locations of down/broken primary and secondary wire

‐ 2 damaged insulators

 

Southdown Sub – 100% complete with damage assessment


‐ 28 broken poles

‐ 28 leaning/down poles

‐ 85 different locations of down/broken primary and secondary wire


‐ 16 damaged insulators

‐ 34 damaged crossarms

‐ 8 damaged transformers


‐ 10 damaged streetlights

 

GAS

Gas leaks since 8/30/21: 66


Turn Offs since 8/30/21: 142

Locates since 8/30/21: 240