Nearly all Terrebonne Entergy substations have been assessed

Tropical weather on the horizon; Invest 91L has 30 percent chance of formation
September 3, 2021
Southern Axe and South Louisiana’s Veteran Outreach Step Up to Serve the Community
September 3, 2021
Tropical weather on the horizon; Invest 91L has 30 percent chance of formation
September 3, 2021
Southern Axe and South Louisiana’s Veteran Outreach Step Up to Serve the Community
September 3, 2021
Terrebonne Office of Homeland Security and Emergency Preparedness provided an Entergy 7pm update, 9/3:
Today we received 200 additional Linemen to help with the restoration process.
-Klondyke Rd. has been successfully cleared to allow large machinery to be transported.
Below is an update on damage assessment in the area:
Gibson Substation – 33% assessed, no broken poles identified at this time. We have assessed everything that is truck accessible. The rest will need special equipment, which is on the way.
Houma Substation – 95% assessed at this point.
Humphrey Substation – 100% assessed.
Montegut Substation – 100% assessed.
Ridgefield Substation – 100% assessed.
Schriever Substation – 100% assessed.
Southland Substation – 100% assessed.
Terrebonne Substation – 100% assessed.
Coteau Substation – 100% assessed.
Chauvin Substation – 100% assessed.
Cascade Substation – 100% assessed.
We expect to have all damage assessment completed by the end of the day tomorrow (9/4).
We still expect the Transmission service to substations in this area to be restored by 9/8.
We still expect to have FULL restoration to EVERYONE that can safely take power by 9/29. ( Some residents may get power sooner. The 9/29 date is the estimate to have the entire parish restored )
Keep hanging in there Terrebonne, progress is being made.